Hiring a quality Unbonded Post-Tension Supplier can be the difference between a smooth construction project and a problematic situation. The Post-Tension (PT) supplier will play a key role in your reinforced concrete project. Therefore, general contractors and concrete contractors need to choose wisely.
Link to Ruiyi
Aside from checking whether the project has been bid per specifications, the following are some questions to ask PT suppliers before awarding the job:
What is your proposed pour sequence?
Unless the construction joints and pour numbers have been referenced on the structural drawings, a PT supplier will have to assume a pour sequence for bidding purposes. If you and your PT supplier had different pour sequences in mind, then time may be wasted in the shop drawing stage. It’s best to be on the same page prior to the contract award.
How many trucks (or deliveries) have you included in your proposal?
If your construction site has limited lay-down areas, then you may not want full truck-load deliveries from your PT Supplier. Your PT Supplier should provide the construction materials per your schedule, but it’s always good idea to let them know the plan.
What previous PT projects have has the PT Supplier worked on that are similar to this project?
Whereas having the lowest price is important during bidding, but hiring a Post-Tensioning Supplier with the right expertise could help you avoid losing money during construction. There may be unique challenges in your construction project that need to be overcome in a timely and cost-effective manner. As with other construction trades, experience matters.
How many sets of stressing equipment will you provide and for how long?
Most PT specifications require at least 2 sets of stressing equipment at the construction site. If one set goes down, then having a backup set can help maintain the schedule. For larger projects with multiple crews, a contractor may require more than 2 sets. As with other rented equipment, the rental period may vary depending on the duration of the project.
– Neel Khosa, Vice President, AMSYSCO
_________________________________________________
Copyright © 2011 by AMSYSCO, Inc. All rights reserved.
Concrete
Post-tension Slab Checklist
copyright 2007 Marshall Hansen
Scope/contract issues
Pre-pour
For more information, please visit post tension system supplier.
Related links:Pour
Post pour/finishing
After you discover the plumber, electrician, other sub or architect/engineer omitted a sleeve, conduit, anchor, piling, footing, whatever and now have to break the slab to replace, install, remove, repair, etc – what shall I do?
Tendon Repair
Did you attempt to repair plumbing, electrical, sleeves without calling the lab for a locate, find a broken tendon after a sub installed a tub, anchor plate, etc? The slab is over-engineered and depending on the location of the broken tendon a repair may not be required. This is a decision only the PT engineer can make. Prepare an RFI with the location clearly described and marked on a tendon layout diagram from the plans, ask if repair is necessary then send RFI and follow RFI response instructions.
If repair is required coordinate with repair tech and determine what prep work is needed to complete the job.
Check revision date for updates. Work safe.
Marshall
More
Like
Loading...
For more bulk supply post tension anchorinformation, please contact us. We will provide professional answers.
If you are interested in sending in a Guest Blogger Submission,welcome to write for us!
All Comments ( 0 )